Bonding begins with a construction cost worksheet filled in by the design engineer. The worksheet is then submitted with the street improvement plans to the plan check section with the rest of the first submittal package for review. The cost estmate needs to include all items within the road right-of-way. The storm drain facilities will be included with the roadwork unless there are flood control facilities, then the storm drain items will be calculated by flood Control.
If this is for a map, survey will provide the monmentation bond amounts. Once all items are covred the Transporation plan check will prepare a fees and securiy report and transmit the report to the Adminstrative Services Analyst int the Construction Division for processing.